Invenio Protocols / Research / Commercial brief 01
Ireland · Digital infrastructure
Prove the power before the site.
For an Irish data-centre commitment, a credible electricity route is part of the commercial proposition. A location, a power headline and an operating date are different things.
§ 01 The assessment
Treat power as a chain of evidence.
Invenio assessment · Evidence grade 04
A buyer or developer should test whether the demand connection, supporting generation, network works and operating conditions can reach the required position together. An attractive site can still have an unproven route to usable capacity.
Our commercial reading is to separate what is contracted, what is conditional and what is only proposed before relying on a delivery programme. An electricity consumption statistic or regional capacity indication cannot establish the position of an individual project.
This is analytical judgement from the records below, not a determination that any named site can or cannot connect.
§ 02 The reported record
What the public sources establish.
- 01
Reported data · Grade 01
Demand has continued to grow.
The CSO's 2025 release reports data-centre metered consumption of 7,663 GWh, a 23% share of Ireland's total metered electricity use. It reports 10% growth from the revised 2024 figure of 6,973 GWh. These are consumption figures, not spare network capacity or a count of deliverable projects. [1]
- 02
Published policy · Grade 01
The connection package extends beyond the demand site.
The CRU's 12 December 2025 decision requires data centres at or above 10 MVA to provide separately metered, dispatchable generation or storage on site or nearby, with de-rated capacity matching their import requirement and market participation. The policy also requires at least 80% of annual demand to be met by additional renewable electricity generated in Ireland, with six years from energisation to meet that level. Smaller projects and applications already being processed under the previous direction have different treatment. [2]
- 03
Published process · Grade 01
An offer timetable is conditional—and stops at the offer.
EirGrid's May 2026 process gives approximately 7.5 calendar months to issue a demand connection offer where associated generation has already received its offers, assuming a complete application and no clarification. It gives up to 18 months where associated generation has only just applied. Both periods run from receipt of application and fee to an offer, not to energisation. [3]
- 04
Published locational assessment · Grade 01
A regional possibility is not a secured connection.
EirGrid's May 2026 overview describes greater Dublin as fully constrained. It identifies potential on parts of the western 220 kV network, subject to individual technical assessment, and says capacity is secured only when a connection agreement is executed. It also cautions that work programmes at many 220 kV substations point to new connections from the mid-2030s. Those statements cannot be converted into an available-MW promise for a particular site. [4]
- 05
Recent technical change · Grade 01
Operating compliance also belongs in the review.
The CRU approved Grid Code modification MPID 345 on 22 September 2026, introducing disturbance-response requirements for current and future transmission-connected demand facilities. EirGrid lists the change as effective from 27 October 2026. [5] [6]
Question to resolve: what compliance or derogation position applies to the project, alongside its connection documents?
§ 03 Commercial implications
Assess the dependency, then the date.
For a site buyer: distinguish ownership or planning progress from the electricity position. A vendor's schedule should identify the documentary basis for the requested import capacity, ramp-up and delivery date. Ask which statements are operator-confirmed and which remain assumptions.
For a developer or occupier: examine the generation and renewable projects supporting the demand application. Their contracting, connection status and delivery sequence can sit on the same critical path as the building. A single date for the campus can conceal several separately controlled dependencies.
For an adviser assessing a transaction: keep these dependencies visible in the commercial assessment. Test the effects of delayed capacity, a slower ramp or additional works on the proposed operating plan. Technical feasibility, contractual protection and valuation require the relevant specialist work; this brief does not supply those conclusions.
These are Invenio's analytical implications. The published sources do not establish a site's price, profitability, funding position or probability of connection. The next useful step is a project-specific evidence request, not a general conclusion about the whole market.
§ 04 Questions to resolve
Six records to request before relying on the programme.
- Demand connection
- The application, offer or executed agreement; counterparty; import capacity; ramp profile; conditions and expiry dates.
- Supporting power
- The identified generation or storage projects, their delivery status and the evidence of the relevant commercial relationships.
- Renewable pathway
- The nominated projects, additionality basis, connection status and programme for meeting the applicable annual requirement.
- Network dependencies
- Operator correspondence identifying required works, technical assessments, responsibility and the assumptions behind target dates.
- Operating conditions
- The applicable Grid Code requirements, study results and any site-specific compliance or derogation conditions, reviewed by technical advisers.
- Commercial exposure
- The commitments falling due before those dependencies resolve, and the contractual treatment of delay or reduced usable capacity.
This is a research agenda, not confirmation that these documents exist for any particular project or that the list completes its diligence.
§ 05 Sources and limits
A dated, inspectable basis.
- CSO — Data Centres Metered Electricity Consumption 2025. Key findings and Table 1; release index, dated 7 July 2026. Figures and year comparisons above use this release's revised series. The index and body identify publication in 2026; the key-findings header carries an inconsistent 2025 date.
- CRU — Large Energy Users Connection Policy. Decision CRU/2025236, 12 December 2025, printed pp. 3–5. This is a selective summary, not the full requirements or an interpretation of a particular application.
- EirGrid — Data Centre Connection Offer Process and Policy. Version 3, 20 May 2026, pp. 3–4. Processing periods depend on the stated conditions and end at an offer.
- EirGrid — Data Centre Constrained Area Overview. 20 May 2026, pp. 11–12. Locational indications remain conditional and do not allocate capacity.
- CRU — MPID 345 decision. Approval and compliance framework, 22 September 2026. The technical requirements cover transmission-connected demand facilities.
- EirGrid — Grid Code modifications register. MPID 345 entry, showing approval effective 27 October 2026.
Boundary. Sources checked on 5 November 2026. This public-source brief covers selected national records and new transmission-connected proposals at 10 MVA or above. It does not verify a named site's connection, planning, contracts, engineering, legal position or financial value. Confirm current project-specific requirements with the relevant operator and specialist advisers before a commitment. CSO consumption data are subject to revision; see its background notes.
Initial publication: 5 November 2026. Reported-source statements are identified as grade 01; Invenio assessment is grade 04 under the published evidence framework. The brief is research, not legal, engineering, valuation or regulated investment advice.
§ 06 Your decision
Put a defined question under examination.