Invenio Protocols

Can the Naas buyer wait for power?

Published · Last updated

A buyer reviewing the Herbata campus option in Naas cannot price the right to wait from the seller’s put and the power schedule alone. A separate 2025 debt agreement required e2 to cause the buyer to exercise its call during the applicable period. The public records we examined do not show that a separate fee buys more time, when it would become non-refundable or whether the buyer could wait for grid confirmation without losing its rights.

Who can start the clock?

Nabors Energy Transition Corp. II’s November 2025 filing describes an April 2024 agreement covering Herbata’s shares and the campus. Receipt of the final applicable planning permissions would open a six-month window for Herbata’s put. Herbata could require e2, through Mission Critical, to purchase. The filing describes a buyer call available if the put has not been exercised, up to the reported endpoint. The underlying agreement defines the two periods. Read alone, that account leaves room for a buyer to assume that inaction by the seller preserves a choice. Nabors Energy Transition Corp. II, quarterly filing, p. 28

On 14 October 2025 e2 entered a secured note agreement. Until its defined Payment in Full, §7.8 required e2 to cause Mission Critical E2 Limited or a permitted successor to exercise the call in its period, fulfil its obligations on a valid put and preserve the option rights. Section 7.2(d) separately required notice to the noteholder of the start of either period and of relevant notices, promptly and within ten business days. That notice deadline does not extend the option period. Section 9.3(a) specifies no five- or thirty-day cure period for a §7 failure. Secured note, §§7, 7.2(d), 7.8 and 9.3

This changes the order of diligence. If the covenant remains effective and the call period opens, waiting for the seller to act could also expose the borrower under its financing. A change agreed with the seller alone might leave that obligation in place. If the secured obligations have been paid in full, or the parties have signed an applicable waiver, reassess the remaining option rights. The note makes waivers specific to their purpose. Secured note, §§8.10, 12.8 and 12.11 and definition of Payment in Full

Which Irish record could change the decision?

The campus appeal is PL09.323677. An Coimisiún Pleanála’s entry records lodgement on 16 September 2025. At our check, its decision field showed a target date and no final order. VA09.323929 concerns the separate proposed substation. Neither entry establishes receipt of the permissions defined by the contract, the exercise of an option, or electricity available to the campus. Campus appeal · Substation application

Kildare County Council’s 20 August 2025 notification of its decision to grant made the timing risk specific. Condition 4 required evidence before commencement of a formal EirGrid connection covering the full electrical load across all phases. Construction would await the planning authority’s written satisfaction. The stated gas-turbine uses were limited to operator-requested backup during grid constraints, emergencies and export. Condition 76 also required gas and grid connection consents before development. If those terms survive appeal and receipt of the final permission qualifies under the option, a purchase window could open while the first phase still lacks clearance to start. A grid letter for the first hall alone would leave the all-phases test unresolved. Council notification, pp. 2, 6 and 21

Herbata’s March 2026 submission described on-site gas generation and renewables and said it intended to seek grid connection once EirGrid published its process. That describes the applicant’s proposed supply arrangements at the time. For any underwritten operating phase, ask which combination of fuel, operating permission, commissioned plant and contracted import must be available, by when and on what terms. A planning event may matter to the acquisition well before the records establish that power can serve the phase. Herbata’s response, §3.4.1.1–3

Position established by counsel Next action for the transaction committee
The call period and the continuing covenant both apply. No applicable relief is evidenced. Put the exercise and notice timetable before counsel and the funding decision-maker immediately. Obtain any required agreement from the parties before relying on a deferral.
Payment in Full or a signed waiver covering the proposed delay is evidenced. Check surviving seller rights and all other operative terms. Value any remaining right to wait against the phase’s delivery path.
The permission trigger, debt position, or scope of relief is unresolved. If either period is known to have begun, send its deadline and notice log to counsel immediately while clarifying debt status. Obtain the final order and evidence of receipt, operative option, notice log, payoff or waiver and current noteholder record. Quantify no discretionary extension on the strength of the planning calendar alone.

Before paying an option fee

The public records examined establish no separate fee that purchases diligence time, no date on which such a fee becomes non-refundable, and no right to wait for grid confirmation without risking the option. Ask for the executed consideration and exercise clause and its schedules. They should specify what the money buys, when it is due, credited, refunded or forfeited, who may withdraw or compel purchase, and the expiry, extension price, notice and cure terms. Check whether an extension lasts until qualifying permission and all-phase grid confirmation, and whether a signed financing waiver covers the same delay. Until those terms are evidenced, the committee cannot treat a proposed fee as the maximum loss.

Evidence limits

Conditional judgment. The executed debt instrument establishes what e2 agreed in 2025. We examined a summary of the option and later financial disclosure. We did not verify the final disposition or discharge of the county conditions, the scope of any operative energy-services agreement, the current note balance or holder, all amendments, an effective waiver, receipt of a qualifying grant, any exercise, default or payment. Settlement income reported by Nabors Industries through September 2026 does not establish the note’s contractual Payment in Full. The records leave the purpose and irreversibility of any fee unresolved, along with any right to wait for grid confirmation and the consents it requires. We have no verified service date, project carrying cost or actual committee decision. No price or delivery date is estimated. Nabors Industries, September 2026 quarterly filing, special-purpose acquisition company discussion

Our inference concerns what to verify before the next commitment. The financing covenant itself is explicit. A qualifying order and receipt, an up-to-date payoff or signed waiver, or revised option terms could reverse the diligence conclusion. Review on 20 November 2026 and on any such event. For a transaction-specific review, bring the operative option, financing instruments, relevant orders and phase delivery records together.

Evidence review completed 21 November 2026 at 02:10 Dublin time. The Commission’s 2 April letter gave no replacement date for deciding the campus appeal. The records we reviewed still do not establish that the buyer received a qualifying permission, that a fee secures an enforceable extension, or that the financing permits the proposed delay. Our assessment remains conditional.

First edition. No corrections recorded. Contact Invenio about a correction.